Scheduled Power Interruption affecting some parts of North and City South area on September 25 & 26, 2024.
When: | September 25, 2024 (Wed): 30 minutes Switching Isolation: anytime between 12:00 AM to 1:00 AM Switching Normalization: anytime between 4:00 AM to 5:00 AM |
Customers Affected: | Whole Tadeco area from Nanyo, New Malitbog, Manay, Libertad, San Miguel, Magsaysay, Dapecol going to Alejal, including Biopulp; Whole of Sto Tomas areas going to Katipunan, Luna, and nearby areas |
Reason: | To facilitate the tapping of the 69kV for the New Gredu Substation |
When: | September 25, 2024 (Wed): 7:00 AM to 3:00 PM |
Customers Affected: | Some parts of Villa De Mercedes Residential Resort Subdivision, Sitio Magsaysay, Sitio Habana, UrbanEast Field Office OutRidge, Acacia, Ambis, Magsaysay, Brgy. Catigan, Toril; Judith Farms, Dayap Compound, Sitio Fagel, Sitio Oval, Cogon, Brgy. Sirawan, Davao City |
Reason: | To conduct line maintenance activity in the area |
When: | September 26, 2024 (Thu): 9:00 AM to 2:00 PM |
Customers Affected: | Some parts of Diamond Street, Magsaysay Street, Villa Grande, Dona Rosa Subdivision, Lizada, Toril, Davao City |
Reason: | To conduct line maintenance activity in the area |